Stripe or block installation method of composite panel forming machine The stripe or block installation method refers to dividing the grid frame into strips or blocks. The units are hoisted by lifting equipment to a high-altitude design position and placed in place, and then installed as a whole. method.

The stripe is divided into several sections along the long span of the grid, and the width of each segment can be from one grid to three grids, and the length is the span of the short span of the grid. The block is divided along the longitudinal direction of the grid. The shape of the rear unit is rectangular or square. The weight of each unit of the composite plate tile press is based on the lifting capacity of the existing lifting equipment on site.

Most of the welding and splicing work of the split or block installation method of the composite board forming machine is performed on the ground, which is conducive to improving the quality of the project and saves most of the assembly brackets. Since the existing single lifting equipment has been considered at the time Capacity, can make full use of the existing equipment on the construction site, reduce the rental cost of lifting equipment, high-altitude bulk method of the composite board machine, high-altitude bulk method refers to the small assembly unit or bulk (single rod and single node) directly at the design Total fight method.

The high-altitude bulk method of the composite board forming machine includes the full support method (that is, full-frame scaffolding) and the overhang method. The full support method is mostly used for assembly of parts, and the overhang method is mostly used for small units assembled at high altitude. Assembly at high altitude does not require large lifting equipment, but because of the large-scale assembly support, a large amount of scaffolding materials are required.


Contact Us
Follow Us